Long-awaited water plant installation underway in Tuluksak

The community of Tuluksak originally expected to have the portable water plant months ago. After the Tuluksak washateria fire, the community lived off donated bottled water for a month and a half. Then, in early March, the Yukon-Kuskokwim Health Corporation was able to restore access to running water.

YKHC installed a system that brought water from the Tuluksak River to the school, but a KYUK investigation found that many people in town did not drink the water. The school is located on the outskirts of town and access to water was limited both by the school’s opening hours and by its storage tanks.

Courtesy of the Yukon Kuskokwim Health Corporation

The community was waiting for another solution: a portable water plant that YKHC would loan to Tuluksak for the next several years until a permanent water plant and laundromat could be built. The new water plant promised to be located in a more central location in the city and to provide much more water storage.

Although the aquatic plant is portable, it is not that easy to move. So when it came to transporting it, Faulkner and Walsh Constructors, the delivery company, was plagued by thinning river ice. The conditions of the ice road were too dangerous for them to drive it from Bethel. For a brief moment, the Army National Guard thought that maybe they could fly the portable water plant using a Chinook helicopter, the same helicopter used to pull off the “Into” bus. The Wild ‘from a remote area near Denali National Park.

Eventually, plans were put on hold until conditions in the river were stable enough to break into the portable water plant, which Faulkner and Walsh were able to do on June 10. Now, according to YKHC, workers are setting up the plant and hope to have it in place. and running later this summer.

The next step in the process is to build a new permanent water treatment plant for the community. YKHC is working with the Alaska Native Tribal Health Consortium, Village Safe Water, and the CRW Engineering Group to obtain updated cost estimates and timelines. Previously, agencies had estimated a figure of $ 8.2 million and a timeline for the summer of 2023.